Evaluation of the tender results of forest road constructions: A case study in Bolu Regional Directorate
The construction of forest roads in Turkey follows a tender process conducted by the General Directorate of Forestry. The amount of work (i.e., excavation volume) is estimated for the approximate cost schedule required for the tender. Unexpected disputes have occurred during the process of finalizing the contracts because measurements are determined by a preliminary survey done prior to preparation of a detailed project proposal. The aim of this study was to compare the road construction data that was calculated during the tender process to the exact values that were obtained as a result of construction. A total of 34 forest roads constructed by Bolu Forest Regional Directorate between 2007 and 2014 were studied. Data were obtained from the tender dossiers to evaluate and compare the cost estimated for the tenders to the actual progress values (excavation quantities, excavation features and costs) of these projects. In addition, these roads have been evaluated according to forest road technical standards. The total length of the assessed roads was 73,879 m, the total costs were USD 977,138, and a total of 726,366 m3 was excavated during the construction of these roads. Paired sample t-tests demonstrated a statistical difference between the tender cost estimates and the progress payment amounts, and between the estimated amounts of very hard rock excavation and the actual amounts of very hard rock excavation.
Fen > Mühendislik > Orman Mühendisliği
DergiAraştırma MakalesiErişime Açık
  • Ozdamar, K., 2002. Statistical Data Analysis with Packet Programs, Kaan Bookstore Press, 4. Edition, Eskisehir. (in Turkish).
  • GDF, 2015. Turkish Forests. https://www.ogm.gov.tr/ekutuphane/Yayinlar/Türkiye%20Orman%20Varlığı-2015.pdf (Accessed: 19 December 2016) (in Turkish).
  • GDF, 2008. Forest Roads Planning, Construction and Maintenance. Turkish Republic, Environment and Forestry Ministry, General Directorate of Forestry Press, Ankara. (in Turkish).
  • Karabacak, M. 2010. The Investigation of Approximate Cost and Progress Payment for Forest Roads to be Built in Lakes Region of Turkey. MSc thesis, Karadeniz Technical University, Institute of Natural Sciences.
  • Hasdemir, M. 1995. Cost Calculations on Forest Road networks, Journal of the Faculty of Forestry Istanbul University 45 (1-2/B): 61-72.
  • Gumus, S., Turk, Y., Arıcak, B. 2015. Investigation of Approximate Cost and Progress Payment in Forest Road Construction Process, Kastamonu University Journal of Forestry Faculty 15 (1): 6-14.
  • FAO, 1992. Cost control in forest harvesting and road construction, FAO Forestry Paper 99, 106 pp, Rome.
  • Erdas, O., Acar, H.H., Tunay, M., Karaman, A., 1995. Forestry Work and Production in Turkey, Forest Roads, Forest Products Transportation, Mechanization in Forestry and Problems Related to Property-Cadastral and Suggested Solutions, Turkey Forestry Report, Karadeniz Technical University, Faculty of Forestry Pres, Trbazon.
  • Erdas, O. 1997. Forest Roads I-II. Karadeniz Technical University Pres, Trabzon. (in Turkish).
  • Erbas, F.D. 2010. The Investigation of Approximate Cost and Progress Payment for Forest Roads to be Built on Mountainouis Terrain. MSc thesis, Karadeniz Technical University, Institute of Natural Sciences.
  • Acar, H.H., Eker, M., Coskun, N., 2003. A Research on the Determination of the Forest Roads Graundbase Type by Terrestrial Methods. Proceeding cd of Austria, High Tech Forest Operations for Mountainous Terrain. October 5-9, Schlaegl, Austria.